The EU procurement thresholds fell on 1 January 2026, services included. For transport contracts that shifts the line between a national procedure and an EU-wide tender.

15 min read

Key takeaways

Since 1 January 2026 a municipal transport contract must be tendered EU-wide once its estimated net value reaches 216,000 euros. For federal supreme authorities the threshold is 140,000 euros net. What counts is the estimated total across the full contract term including every extension option, not the annual value of a single lot.

  • Since 1 January 2026, supply and service contracts awarded by the übrige öffentliche Auftraggeber (all contracting authorities other than the federal top-tier ones), which covers the federal states, districts, municipalities and municipal bodies, fall under an EU threshold of EUR 216,000 net. For upper and supreme federal authorities the figure is EUR 140,000 net.
  • The current figures rest on Commission Delegated Regulations (EU) 2025/2150, 2025/2151 and 2025/2152 of 22 October 2025. They apply for 2026 and 2027.
  • What counts is the estimated total contract value excluding VAT across the entire term, including every extension option and every lot (§ 3 VgV). The annual value of a single lot does not decide the question.
  • Below the EU threshold, national sub-threshold law applies, and for services that mainly means the UVgO (the German procurement rules below the EU thresholds). It only takes effect through budgetary application orders issued by the federal government and the states, which is why it looks different in each state.
  • School and disabled passenger transport is normally tendered under CPV code 60130000-8 (special-purpose road passenger transport). That code does not appear in Annex XIV of Directive 2014/24/EU, so the relaxed threshold of EUR 750,000 for social and other specific services does not apply to pure transport work.

The EU procurement thresholds 2026 took effect on 1 January, and they went down. For supply and service contracts awarded by the übrige öffentliche Auftraggeber (all contracting authorities other than the federal top-tier ones) the line now sits at EUR 216,000 net instead of EUR 221,000, which sounds like a footnote and is not one for transport operators. Far more hangs on that line than the question of where a contract notice appears. Above the threshold, Part 4 of the GWB (the German competition act, which carries the EU procurement rules) applies, with EU-wide publication duties, fixed minimum deadlines and the review application before the Vergabekammer (public procurement tribunal) under § 160 GWB. Below the threshold that primary legal protection does not exist, and a bidder who feels passed over has little in hand beyond a complaint lodged with the contracting authority. The figures, calculations and references below are current as of July 2026.

Which EU thresholds apply to transport contracts in 2026?

Since 1 January 2026 the threshold for public supply and service contracts stands at EUR 216,000 net where the contracting authority belongs to the übrige öffentliche Auftraggeber. That group includes the federal states, districts, municipalities and municipal bodies. Upper and supreme federal authorities sit at EUR 140,000 net. Works contracts and concessions carry a value of EUR 5,404,000. Behind all three figures stand Commission Delegated Regulations (EU) 2025/2150, 2025/2151 and 2025/2152 of 22 October 2025.

EU thresholds, net, for procurement procedures started on or after 1 January 2026. As of July 2026.
Type of contractfrom 1 Jan 2026until 31 Dec 2025
Supplies/services, upper and supreme federal authorities€140,000€143,000
Supplies/services, all other contracting authorities€216,000€221,000
Supplies/services, utilities sector plus defence and security€432,000€443,000
Works contracts and concessions€5,404,000€5,538,000
Social and other specific services (Annex XIV of Directive 2014/24/EU)€750,000€750,000

All figures are net amounts. § 106 paragraph 1 GWB explicitly refers to the estimated contract or agreement value excluding VAT, and paragraph 2 points to the EU directives for the actual amounts. The German legislator therefore does not set the numbers at all. They come from Brussels and reach into national law through that reference.

One value stayed put. The thresholds for social and other specific services under Annex XIV of Directive 2014/24/EU are not covered by the WTO Government Procurement Agreement and were therefore left unchanged. They remain at EUR 750,000 for public contracting authorities and EUR 1,000,000 for utilities. For pure transport work that rarely helps, and the reason follows further down.

Where the figures come from and how long they last

The three delegated regulations of 22 October 2025 were published in the Official Journal of the EU on 23 October 2025 and apply from 1 January 2026. Each of them amends exactly one directive.

  • Delegated Regulation (EU) 2025/2152 amends the classic procurement directive 2014/24/EU. It cuts EUR 5,538,000 to EUR 5,404,000, EUR 143,000 to EUR 140,000 and EUR 221,000 to EUR 216,000.
  • Delegated Regulation (EU) 2025/2150 amends the utilities directive 2014/25/EU. It cuts EUR 443,000 to EUR 432,000 and EUR 5,538,000 to EUR 5,404,000.
  • Delegated Regulation (EU) 2025/2151 amends the concessions directive 2014/23/EU from EUR 5,538,000 to EUR 5,404,000.

For municipal transport contracts, 2025/2152 is therefore the relevant reference. Summaries occasionally cite 2025/2151 at this point, which is wrong.

Why the values fell at all is set out in the recitals of the regulations. The thresholds are tied to the WTO Agreement on Government Procurement, which fixes the amounts in special drawing rights. Every two years the Commission checks whether the euro figures in the directives still match the agreement and resets them with effect from 1 January. It is an exchange rate calculation rather than a political decision, and it can swing either way.

To classify a specific procedure, the start of the procedure is what counts. The new values apply to procurement procedures started on or after 1 January 2026 and remain applicable until 31 December 2027. Under § 3 paragraph 3 VgV the decisive day is the one on which the contract notice is dispatched or the procedure is otherwise initiated. Neither the award nor the contract start date matters.

How is the contract value calculated for transport services?

A transport contract has to be tendered EU-wide as soon as the estimated total net contract value reaches the applicable threshold, so EUR 216,000 for municipal contracting authorities. The calculation rules sit in § 3 VgV (the German regulation on the award of public contracts). That is also where most of the mistakes happen.

Five rules from § 3 VgV

  • Options count. Under § 3 paragraph 1 VgV any options and contract extensions must be taken into account, even where it is entirely open whether they will ever be exercised.
  • Lots are added together. Where a service leads to a contract split into several lots, § 3 paragraph 7 VgV requires the estimated total value of all lots to be used. If that total reaches the threshold, the VgV governs the award of every lot, the small ones included.
  • Splitting to circumvent the rules is not allowed. § 3 paragraph 2 VgV prohibits both the choice of calculation method and the subdivision of a contract where the intention is to escape EU procurement law.
  • Without a total price, the 48-month cap applies. For service contracts with no stated total price, an indefinite term or a term beyond 48 months means 48 times the monthly value must be used (§ 3 paragraph 11 VgV).
  • Recurring contracts are rolled forward. For regularly recurring contracts, § 3 paragraph 10 VgV allows the actual total value of the previous year to be used, adjusted for expected changes in volume and cost.

Worked example: school transport in four lots

A district awards freigestellter Schülerverkehr (school transport exempted from the public transport licensing regime) to the special-needs schools in its area across four lots. The base term runs two school years, with an option to extend twice by one school year each.

  1. Set the annual value per lotLot A EUR 95,000, lot B EUR 70,000, lot C EUR 45,000, lot D EUR 30,000, each net per school year. Total EUR 240,000 a year.
  2. Extrapolate the base termTwo school years give EUR 480,000. That figure alone sits well above EUR 216,000.
  3. Add the option yearsWith both extension options the contract spans four school years and an estimated total value of EUR 960,000 net. This is the figure that decides the type of procedure.
  4. Check the de minimis exemption for small lotsUnder § 3 paragraph 9 VgV a single lot may be awarded nationally if its estimated net value stays below EUR 80,000 and the sum of these small lots does not exceed 20 per cent of the total value. Lot D reaches EUR 120,000 over four years and therefore breaks the EUR 80,000 limit, even though its annual value is only EUR 30,000.

Why the de minimis limit almost never holds

The last step is where things go wrong most often. The EUR 80,000 in § 3 paragraph 9 VgV refers to the value of the lot across the entire term, not to a single contract year. In multi-year contracts with option years, practically every serious lot drops out of the exemption. A contracting authority that builds its procedure on it risks having the whole thing reopened after a complaint.

What applies below the EU thresholds?

If the estimated total value stays under EUR 216,000, Part 4 of the GWB does not bite. National sub-threshold law applies instead, and for supplies and services that mainly means the Unterschwellenvergabeordnung (UVgO), the procurement rules below the EU thresholds. The UVgO is not a directly binding legal norm, though. It takes effect through budgetary application orders issued by the federal government and the states, and those differ, sometimes even within one state between state and municipal authorities.

Whether a contracting authority in your district has to obtain three quotes from EUR 25,000 or only runs an open tender from EUR 50,000 is therefore not written in the UVgO but in the procurement rules of the state in question. Anyone bidding across several states should know these value limits state by state.

The differences are tangible. Federal contracting authorities initially worked with a temporary limit of EUR 15,000 net for Direktauftrag (direct award without a competitive procedure), departing from § 14 UVgO; the Vergabebeschleunigungsgesetz (procurement acceleration act), in force since 1 July 2026, raised it to EUR 50,000 net. States and municipalities set their own, sometimes markedly different limits for Direktauftrag, Verhandlungsvergabe (negotiated award) and beschränkte Ausschreibung (restricted invitation to tender). On top of that come the Landesvergabegesetze (state procurement acts) with collective-agreement compliance, minimum pay and evidence requirements, which in some states apply below the EU thresholds too and hang on their own value limits.

Below the threshold does not mean informal

Even below the EU thresholds, the procurement principles of the UVgO remain binding, so competition, transparency, equal treatment, economy and efficiency. What falls away is primary legal protection before the Vergabekammer. The contracting authority still has to document a procedure that can be followed and understood.

Movement has been announced for the coming months. On 30 June 2026 the Federal Ministry for Economic Affairs and Energy presented a draft for a fundamental revision of the UVgO, currently being coordinated between the federal government and the states. Until the states update their application orders, the current state rules remain decisive.

Where transport tenders are published

Above the thresholds there is no way around Tenders Electronic Daily (TED), the supplement to the Official Journal of the EU. § 40 VgV sets out an order of publication that matters in practice for market monitoring. National publication may only follow once the EU Publications Office has published the notice, or once 48 hours have passed since the confirmation of receipt. It may also contain no information that was not sent to Brussels as well. Finding a notice first on a state platform therefore gives you no head start over European competitors.

Alongside that, oeffentlichevergabe.de, the notice service of the Datenservice Öffentlicher Einkauf at the Beschaffungsamt des BMI (the procurement office of the federal interior ministry), pools EU-wide and national notices from federal, state and municipal bodies. The search is open without registration. For EU-wide notices, the standardised eForms have been mandatory since 25 October 2023. The procedure itself, with tender documents, bidder questions and submission, then runs on the relevant state platform.

For searching, the CPV code is the most usable filter. School, disabled passenger and sheltered-workshop journeys are overwhelmingly published under [60130000-8 (special-purpose road passenger transport)](https://ted.europa.eu/en/simap/cpv). A standing filter on that code plus the districts in your own catchment area catches live tenders and, alongside them, the award notices for contracts already placed. Their contract terms tell you when the next round is due.

Code 60130000-8 does not appear in Annex XIV of Directive 2014/24/EU. The lighter regime for social and other specific services under § 130 GWB, which carries the EUR 750,000 figure, therefore does not apply to pure transport work. The EUR 216,000 stands. The picture changes where a contract combines transport with care and supervision. Then § 110 GWB makes the main subject matter decisive, and that is determined by whichever part of the service carries the higher estimated value.

What transport operators should take from the thresholds in practice

If even a mid-sized school transport award with option years almost inevitably lands above the threshold, the EU-wide procedure with formal deadlines and documented suitability checks becomes the normal case. An operator can plan around that.

More important than the type of procedure is the length of the commitment. It runs across the full term including options, four school years in the example above. Anyone checking a lot against the vehicle and driver capacity available today is answering the wrong question. What matters is whether that capacity still holds in year four, and at what cost. It only becomes reliable with actual operating data, meaning real route times, empty kilometres, waiting times and cancellation rates. Dispatch and route planning systems produce these numbers anyway; the question is whether the last twelve months are available in a form you can analyse or have to be reconstructed from paper logbooks. How that turns into a defensible rate per kilometre is something we worked through in a separate piece on cost per kilometre in minibus operations.

On suitability evidence, things eased on 1 July 2026. For awards above the EU thresholds, the Vergabebeschleunigungsgesetz makes self-declarations the default; the actual evidence is generally requested only from the company set to receive the award. That shortens bid preparation noticeably. You still have to keep the documents ready, because once the award recommendation is out there is little time for follow-up requests.

  • Calculate the total value of a lot across the full term including all option years, never the annual value on its own.
  • Check whether vehicle and driver capacity still holds in the final option year, including replacement vehicles and cover arrangements.
  • Keep Führungszeugnisse (police clearance certificates), passenger transport driving permits, insurance certificates and tax clearance certificates continuously up to date.
  • Draw your costing basis from the actual data of the last twelve months, meaning kilometres, hours, empty runs and cancellation rates.
  • Set up CPV 60130000-8 as a standing filter on TED and oeffentlichevergabe.de and read the award notices alongside the live tenders.
  • Check the Landesvergabegesetz of the contracting authority in question, because collective-agreement and minimum pay requirements shift the staff costs in your calculation.

On the other side of the table the reverse applies. A lot structure that artificially pushes individual lots below EUR 80,000 will usually not survive scrutiny under § 3 paragraphs 2 and 9 VgV. Anyone wanting to reach the market of smaller transport operators gets further with a sensible lot structure and proportionate suitability requirements than with the choice of procedure. What that involves from the perspective of a Schulträger (the public body responsible for the school) is set out in our overview for schools and school authorities.

Frequently asked questions

Since 1 January 2026 the EU threshold has been EUR 216,000 net for supply and service contracts awarded by all contracting authorities other than the federal top tier, so by federal states, districts and municipalities among others. For upper and supreme federal authorities it is EUR 140,000 net. The legal basis consists of Commission Delegated Regulations (EU) 2025/2150, 2025/2151 and 2025/2152 of 22 October 2025, published in the Official Journal of the EU on 23 October 2025. The values apply for 2026 and 2027; the next adjustment is expected on 1 January 2028.

As soon as the estimated total net contract value reaches the applicable EU threshold, which for municipal contracting authorities means EUR 216,000. What counts is the value across the entire term including all extension options and all lots, not the annual value of a single lot. If the total value of all lots reaches the threshold, EU procurement law applies under section 3 paragraph 7 VgV to the award of every individual lot.

Net, that is excluding VAT. Section 106 paragraph 1 GWB explicitly refers to the estimated contract or agreement value excluding VAT. Under section 3 paragraph 1 VgV the basis for calculation is the expected total value of the intended service across the whole contract term, including any options and contract extensions.

As a rule it does not. School and disabled passenger transport is normally tendered under CPV code 60130000-8 for special-purpose road passenger transport, and that code does not appear in Annex XIV of Directive 2014/24/EU. The lighter regime for social and other specific services under section 130 GWB therefore does not apply to pure transport work. Where a contract also contains substantial care and supervision elements, section 110 GWB makes the main subject matter decisive, determined by whichever part of the service carries the higher estimated value.

Below the thresholds, national sub-threshold law applies, and for services that means the Unterschwellenvergabeordnung (UVgO) in particular. It only takes effect through budgetary application orders issued by the federal government and the states, which is why the specific value limits for direct award, negotiated award and open invitation to tender differ from state to state. The principles of competition, transparency, equal treatment and economy apply there as well. A review application before the procurement tribunal, however, is not available below the thresholds.

Sources

  1. Delegierte Verordnung (EU) 2025/2152 der Kommission vom 22. Oktober 2025 zur Änderung der Richtlinie 2014/24/EUAmtsblatt der Europäischen Union · Thresholds of EUR 5,404,000 / 140,000 / 216,000; published on 23 October 2025
  2. Delegierte Verordnung (EU) 2025/2150 der Kommission vom 22. Oktober 2025 zur Änderung der Richtlinie 2014/25/EUAmtsblatt der Europäischen Union · Utilities directive: EUR 432,000 and EUR 5,404,000
  3. Delegierte Verordnung (EU) 2025/2151 der Kommission vom 22. Oktober 2025 zur Änderung der Richtlinie 2014/23/EUAmtsblatt der Europäischen Union · Concessions: EUR 5,404,000
  4. § 106 GWB, Schwellenwertegesetze-im-internet.de (BMJ) · Net value; reference to the EU directives. As of July 2026
  5. § 110 GWB, Vergabe von öffentlichen Aufträgen und Konzessionen, die verschiedene Leistungen zum Gegenstand habengesetze-im-internet.de (BMJ) · Main subject matter determined by the higher estimated value of the service elements
  6. § 130 GWB, Vergabe von öffentlichen Aufträgen über soziale und andere besondere Dienstleistungengesetze-im-internet.de (BMJ) · Reference to Annex XIV of Directive 2014/24/EU
  7. § 160 GWB, Einleitung, Antraggesetze-im-internet.de (BMJ) · Review application before the procurement tribunal, complaint deadlines
  8. § 3 VgV, Schätzung des Auftragswertsgesetze-im-internet.de (BMJ) · Options, lots, anti-circumvention rule, EUR 80,000 de minimis limit. As of July 2026
  9. § 40 VgV, Veröffentlichung von Bekanntmachungengesetze-im-internet.de (BMJ) · Order of EU and national publication, 48-hour rule
  10. Verfahrensordnung für die Vergabe öffentlicher Liefer- und Dienstleistungsaufträge unterhalb der EU-Schwellenwerte (UVgO), Ausgabe 2017Verwaltungsvorschriften im Internet (BMJ) · Official text, BAnz AT 07.02.2017 B1, corrected BAnz AT 08.02.2017 B1
  11. Neue EU-Schwellenwerte ab 01.01.2026Vergabe.NRW (Ministerium für Wirtschaft, Industrie, Klimaschutz und Energie NRW) · Overview of all values, including the unchanged EUR 750,000
  12. Vergabebeschleunigungsgesetz, Verkündung und InkrafttretenVergabe.NRW (Ministerium für Wirtschaft, Industrie, Klimaschutz und Energie NRW) · BGBl. 2026 I No. 137 of 18 May 2026, in force since 1 July 2026
  13. Neue EU-Schwellenwerte und nationale Anpassungen ab dem 1. Januar 2026CMS Deutschland (secondary source, law firm legal update) · Classification of sub-threshold law, federal direct award at EUR 15,000 departing from § 14 UVgO
  14. Tenders Electronic Daily (TED), Supplement zum Amtsblatt der EUAmt für Veröffentlichungen der Europäischen Union · Mandatory publication venue above the EU thresholds
  15. Common Procurement Vocabulary (CPV), Verordnung (EG) Nr. 213/2008Amt für Veröffentlichungen der Europäischen Union / TED · Official CPV code list, in application since 17 September 2008
  16. eForms, standardisierte BekanntmachungsformulareEuropäische Kommission, GD Binnenmarkt · Mandatory since October 2023
  17. Bekanntmachungsservice des Datenservice Öffentlicher Einkauf (oeffentlichevergabe.de)Beschaffungsamt des BMI · Access without registration; notices from federal, state and municipal bodies

This article reflects the situation at the time of publication and does not replace individual legal or tax advice.

Costing with actual data instead of estimates

Vermo brings dispatch, route planning, a driver app and service records together for passenger transport operators. Once kilometres driven, waiting times and escort services are documented cleanly, lots spanning several contract years can be costed more reliably and evidence reaches contracting authorities faster. What Vermo covers is set out on the home page.

Book a demo call